March 2009
- CMS Finance 9.0 upgrade goes live, replacing version 8.4
October 2008
- Module Work Team sessions are scheduled as follows:
- Reporting Fit/Gap sessions – tentatively scheduled for October 2008
September 2008
- Module Work Team sessions are scheduled as follows:
- Accounts Payable Fit/Gap sessions – 9/9/08 thru 9/11/08
- Purchasing & P-Card Fit/Gap sessions – 9/2/08 thru 9/4/08, 9/16/08 thru 9/18/08
August 2008
July 2007
- July 1—CMS Finance system goes live, replacing the FRS system.
May 2007
- CMS requisition entry will be available June 4th. Training will begin at the end May
January 2007
- Divisional Finance Coordinator’s meeting scheduled for 1/26/06 to review and discuss LCD (labor cost distribution).
- User Work Team sessions are scheduled as follows:
- Department Level Security session – 1/22/07
- Asset Management Fit/Gap session – 1/24/07
- AR & Billing Fit/Gap session – 1/24/07
December 2006
- Divisional Finance Coordinator’s meeting scheduled for 12/8/06.
- User Work Team session is scheduled as follows:
- Recharge Center Fit/Gap session – 12/4/06
- Module Work Team sessions are scheduled as follows:
- Accounts Receivable & Billing Fit/Gap sessions in-process thru December
- Asset Management Fit/Gap sessions in-process thru December
November 2006
- User Work Team sessions are scheduled as follows:
- Accounts Payable Fit/Gap sessions – 11/7/06 thru 11/9/06
- Module Work Team sessions are scheduled as follows:
- Accounts Payable Fit/Gap sessions in-process
- Accounts Receivable & Billing Fit/Gap sessions in-process
- Asset Management Fit/Gap sessions begin 11/14/06
October 2006
- User Work Team sessions are scheduled as follows:
- Procurement Fit/Gap Sessions – 10/3/06 thru 10/5/06
- General Ledger / Budget Fit/Gap Sessions – 10/17/06 thru 10/19/06
- Module Work Team sessions are scheduled as follows:
- Accounts Payable Fit/Gap sessions begin 10/9/06
- Accounts Receivable & Billing Fit/Gap sessions begin 10/31/06

Download the CMS Finance timeline
|
|
 |
|